Month-by-month construction timeline: permits, foundation, structure, finishes. How long to build a house, villa, hotel in Mexico.
Services
Month-by-month construction timeline: permits, foundation, structure, finishes. How long to build a house, villa, hotel in Mexico. We handle everything from design to completion, including all permits and inspections.
Costs
Contact us for a detailed quote tailored to your project. Free consultation and estimate within 24 hours.
Get a Free Quote for Your Project
Response within 2 minutes via WhatsApp
Get Quote Now
Frequently Asked Questions
Weekly photo/video reports every Friday. WhatsApp group with your project manager. Milestone completion notifications with financial summary. Time-lapse camera option ($5,000 MXN/month). You see everything in real-time.
Standard: 10% at contract, 15% at foundation complete, 20% at structure, 15% at roof, 15% at MEP, 15% at finishes, 10% at handover. Never pay ahead of actual progress. Each payment tied to verified milestone completion.
Fixed-timeline contracts include penalty clauses for contractor delays (we absorb cost of extra labor/overtime). Weather delays documented with photos. Material delays mitigated by ordering 4–8 weeks in advance. Weekly schedule updates keep you informed.
Changes before foundation: minimal impact. During structure: moderate cost/time impact. After structure: expensive — may require demolition and rebuilding of affected areas. We strongly recommend finalizing design before permits. Change order process: written request → cost estimate → approval → execution.
Yes — only foundation excavation is significantly affected by heavy rain. Once foundation is poured and cured, construction continues through rain. We use tarps, temporary roofing, and adjust schedules around major storms. Most projects don't need to pause for rain.